|
 |
DAMS, RESERVOIRS and HYDRAULIC STRUCTURES
The following are typical examples of Surface
Water Impoundment projects accomplished or
underway by Denmon Engineering. DE involvement
ranged from being the lead firm for the project
team to develop complex reservoir projects
to providing technical and engineering assistance
to complete:
- Site Evaluation and Selection
- H & H Studies
- Storm Routing
- Firm Water Yields
- Dam Safety
- Stage Reductions
- Additional Hydraulic Control
- Geotechnical and Foundations
- Structural Studies
- Environmental and Permitting
- Master Planning
- Cost Estimating and Feasibility Studies
- Ancillary Facilities
- Construction Management
- Regulatory Coordination
|
 |
Representative examples of the dams and reservoir
projects accomplished by DE are listed below:
Poverty Point Reservoir
The Poverty Point Reservoir in Richland Parish,
Louisiana near the Town of Delhi is an ideal
example of the capacity for the DE Team to
advance complex projects on a "short
tract" schedule. This project, which
is near completion, is a surface impoundment
of approximately 2, 700 acres intended as
a water supply and recreation facility. The
estimated cost is in the vicinity of $15
million dollars.
The development faced significant obstacles
in that it is located in close proximity
to the Poverty Point Commemorative Area that
has received a federal designation as a national monument and has world wide
archeological significance. In addition,
the project is located within the proposed
critical habitat of the Louisiana Black Bear
that is a threatened species under the Endangered
Species Act.
Rising above these obstacles, the DE Team
started work on the project in 1991. All
regulatory permits were gained and construction
began in 1996. The project is scheduled for
completion in 2002. This is an extremely
short project schedule and the DE Team proved
to be up to the challenge.
Bundick Lake Additional Spillway
DE was selected as the lead consultant for
an improvement project on the existing Bundick
Lake in Beauregard Parish, Louisiana, where
adjacent improved residential and commercial
property is suffering from flood damage incurred
through fluctuating pool stages of the lake.
DE performed the necessary hydraulic and
hydrologic studies to model the lake surface
during rainfall, up to and including the
probable maximum flood and designed the alternative
solution best suited for the project. Since
the initial work, the DE Team has carried
the project through surveying, preliminary
engineering studies, conceptual design and
is currently working on the construction
plans for a 1,200-foot spillway addition
estimated at a cost of approximately $18
million dollars.
Bayou DeChene Reservoir
The DE Team was selected to plan, design
and assist in construction management of
a new 1,100 acre reservoir located in Caldwell
Parish, Louisiana. This project is similar
to the Poverty Point Reservoir project. DE
has carried the project through the initial
engineering and environmental studies necessary
to justify the reservoir and to detail the
construction and environmental considerations.
DE is presently preparing plans and specifications
for several phases of the project. The overall
project is estimated to cost approximately
$12 million dollars.
Bayou D'Arbonne Lake Additional Spillway
The DE Team was selected to provide engineering
and environmental services similar to the
Bundick Lake project above. At present, DE
has completed the hydraulic and hydrologic
computer model studies to project the lake
profiles for all events up to and including
the probable maximum flood. DE has also determined
the slab elevation for approximately 700
residential and commercial structures around
the lake and has completed the engineering
and feasibility studies required to document
the best suited alternative for limiting
the pool elevations as a means of minimizing
adjacent property damage.
Red River Navigation Project Three Tributary
Lakes Study
DE acted as a subconsultant to Espey, Huston
& Associates, Inc. which provided the
surveying, structural and civil engineering,
environmental, and geotechnical engineering
necessary to determine the adverse impacts
to the three dams forming Black, Saline,
and Nantucket Lakes, which are adjacent to
the Red River, as a result of the elevated
river stages created by the Red River Navigational
project and to formulate the alternatives
for mitigating any such adverse impacts.
Shallow Water Reservoir for Duty Ferry Farms
The DE Team was selected to design a 550-acre
shallow water reservoir intended for wildlife,
particularly waterfowl, in Catahoula Parish,
Louisiana. The reservoir was constructed
utilizing earthen levees, control structures,
and the pumping capabilities necessary to
fill the reservoir in the fall to accommodate
waterfowl feeding and nesting and allow the
reservoir to be drained in the Spring for
regrowth of natural wetland plants.
Spring Lake Dam Rehabilitation
Denmon Engineering along with its geotechnical
subconsultant, Burns Cooley Dennis, provided
technical support to PBS&J who were ultimately
selected to provide engineering and environmental
studies to rehabilitate the Spring Lake Dam
on the Southwest Texas State University Campus
in San Marcus, Texas. Work completed to date
includes the preparation of a preliminary
engineering report which addresses problems
and solutions at the Spring Lake Dam. Currently,
the dam suffers excessive piping and leaking
and a large cavern has eroded under the stop-log
control structure and stilling basin.
The preliminary engineering report indicates
that the project should be broken into two
phases. The first phase should be an emergency
phase that should isolate the control structure
with the coffer dams, and reinstate the foundation
with pumped concrete grout.
The second phase would rehabilitate the dam
proper by clearing and grading, installation
of a filter cloth and a rock rip-rap blanket
to control piping and seeping and to add
stability, install a toe trench drain to
collect normal seepage and to completely
replace the reinforced concrete control structure
with a gated structure. Estimated cost approximately
$5 million dollars.
Castor Creek Reservoir
The DEC Team was recently selected to provide
all planning, engineering, environmental
and surveying services required to develop
a major reservoir project located in Central
Louisiana to be known as the "Castor
Creek Reservoir." This will be a principal
reservoir project estimated to have approximately
34,000 acres of surface at pool stage with
an average depth of 12 feet and a maximum
depth of 60 feet. The proposed lake will
have a drainage area of approximately 775
square miles and contain approximately 425,000-acre
feet of water at normal pool stage.
The project to be handled by the DEC Team
will be comprehensive including the planning,
design and construction of the dam, control
structures, access roads, required relocations,
recreation facilities and other appurtenances
normally associated with such a complex project.
It is planned that the reservoir will be
used to provide drinking water for a large
area in Central Louisiana and provide significant
fishing and other recreational opportunities.
The lake is anticipated to have approximately
250 miles of shoreline and expected to be
the center stone for a major development
that is to include parks, golf courses, marinas
and other developments.
West Ouachita Reservoir
Denmon Engineering has also recently been
selected to provide site selection and all
planning, engineering, environmental and
surveying services required to develop a
potable water supply and recreational reservoir
complex for west Ouachita Parish, Louisiana.
The project will be comprehensive including
the planning, permitting, design and construction
of the dam, control structures, access roads,
required relocations, recreation facilities
and other appurtenances normally associated
with such a complex project. Estimated Project
Cost: $25 million
Off-Channel Reservoir Project for the Pierce
Ranch Water Right
Denmon Engineering provided the Lower Colorado
River Authority (LCRA) engineering and technical
assistance to evaluate engineering and cost
particulars relative to constructing a 25,000
acre-foot off-channel reservoir to maximize
total yield from the Pierce Ranch Water Right,
of which they were evaluating the purchase.
Two engineering studies were conducted which
evaluated the design particulars and cost
to construct a reservoir on several specific
sites and the hydraulics necessary to divert
water to and from the Colorado River. Studies
were also conducted to determine if construction
of such a reservoir in the flood plain would
have a significant impact on flooding in
the nearby Town of Wharton. LCRA has successfully
concluded the purchase.
Lometa Reservoir
Denmon Engineering provided all engineering
and technical services for an 80-acre off-channel
reservoir for potable water in Lampasas County,
Texas. DE performed all H & H studies,
geotechnical investigations, civil and structural
engineering for the reservoir complex which
included an earthen dam, concrete outlet
works and emergency spillway.
The reservoir did not have sufficient drainage
area and storage to provide needed water
supply. A water intake structure, pumping
plant and pipeline was designed to supplement
the reservoir from the Colorado River approximately
eight (8) miles distant. The project is currently
under construction with Denmon Engineering
providing construction management and inspection.
Pope Westminister Force Main and Stilling
Basin
DE prepared engineering studies and construction
plans and specifications for a 72/96-inch
concrete cylinder force main to carry the
discharge from a 300 cfs pumping station
through a residential neighborhood into Bayou
DeSiard. Owing to the lack of a suitable
discharge site, designed and constructed
a reinforced concrete stilling basin beneath
a major street intersection, one of the streets
being a major arterial traffic route along
the top bank of Bayou DeSiard. Discharge
velocities were very critical on this project
as it discharged into the Bayou DeSiard in
the vicinity of the raw water intake for
the City of Monroe’s drinking water supply.
Estimated cost approximately $2 million dollars.
East Parkview Flood Prevention Project
DE prepared preliminary engineering studies
and construction plans and specifications
to construct a flood prevention project in
the City of Monroe consisting of a back water
prevention levee (dam), reinforced concrete
collection system and a major storm water
pumping station. Estimated cost approximately
$2.5 million dollars.
Forsythe/Chauvin Flood Prevention Project
DE prepared engineering studies and construction
plans and specifications to build a major
back water flood prevention project consisting
of approximately 6,200 linear feet of earthen
levee (dam) with a reinforced concrete overflow
spillway structure and a 40 cfs pumping station
with reinforced concrete stilling basin.
Estimated cost approximately $2 million dollars.
Wilson Point Pumping Plant
DE prepared construction plans and specifications
to build a 75 cfs pumping station where the
mainline Mississippi River levee crossed
a major drainage cannel draining over 10,000
acres. Pumping Plant consisted of a reinforced
concrete structure on a concrete pile foundation
with two diesel driven 75 cfs pumps, discharge
pipes and controls. Estimated cost approximately
$1 million dollars.
Boeuf River Reclamation Project
DE prepared engineering studies and construction
plans and specifications to rehabilitate
a 20 mile stretch of Boeuf River which included
the construction of 3 steel sheet pile and
rock rip-rap overflow weirs and channelization
of approximately 4.5 miles of channel at
a estimated cost of approximately $1.6 million
dollars.
|
|
|